Projects

Renewal of tracks – Docks Shopping Centre & SPRB bridge – Brussels

A brilliant piece of teamwork at Taveirne: renewing the tracks in front of the Docks shopping centre and on the SPRB's new bridge.

Port of Zeebrugge: final major phase

Major works at the port of Zeebrugge are nearing completion. Only finishing works are scheduled for September.

Construction of 3rd and 4th tracks between Bellem and Oostkamp

Two additional tracks are being laid on Belgium’s busiest railway line (L50), between Ghent and Bruges.SNCB is already integrating the new tracks into the June timetable, which will lead to smoother and more punctual train connections.

Renewing tram tracks – Schaerbeek

From March to the end of July 2023, Taveirne renewed the tramline tracks between the Schaarbeek depot and central Brussels.

Renewal of tram tracks – Schaerbeek

During the summer of 2023, Taveirne renewed the line between Schaerbeek station and central Brussels on behalf of STIB, track type jaquette.

Renewal of switches – Lot (Beersel)

In Lot, borough of Beersel, 2 switches were renewed last weekend. Our PEM LEM lorries were used to carry out this work.

Interventie – Brug Demeysluis Oostende

In opdracht van De Lijn Interventie na breuk in het spoor naar de brug aan de Demeysluis, Oostende

Ghent Sint-Pieters master plan

Switches were placed at the Gent Sint-Pieters yard last month in anticipation of the construction of platform tracks 6 and 7.

Placing points and derailment needles – Forest

In early May, Taveirne could be seen at work on a site in Forest installing 4 concrete points and 2 derailment needles.

Renewal of tracks and switches – Brussels

On site in Brussels, Taveirne was responsible for renewing 120 m of track and installing a switch.

Renewal of tracks – Deinze

On site in Brussels, Taveirne was responsible for renewing 120 m of track and installing a switch.

Renewal of points and track equipment – Kortrijk Kortrijk yard:

Renewal of points and track equipment. Also construction of the track.

Remplacement des voies et des aiguillages du chantier 745 – Gand

Quai 745 à Gand Ce projet comprenait : Remplacement des rails/interrupteurs Remplacement de la sous-couche sur une ferme OC Placer des blocs de légion sur une voie principale à Gand afin que cette voie puisse être déplacée ultérieurement.

Renewal of tracks and extension of platforms – Nivelles

In Nivelles, Taveirne was in charge of renewing 2 x 750 m of tracks and extending 2 platforms. On behalf of TUC rail

Track and switches renewal – Brussels South

At Brussels South Station, Taveirne was in charge of renewing the switches and tracks.

Renewal of track and switches – Forest

Taveirne renewed the tracks and switches along the Forest line on behalf of Infrabel.

Construction of tram tracks Avenue Rogier – Schaerbeek

Taveirne was in charge of laying new tram tracks in Schaarbeek, with exchange beams on concrete support. All together on a vibration-free slab.

Tramway construction on Theunis Bridge – Antwerp

In collaboration with Stadsbader and Artes, Taveirne installed the tram tracks on the New Theunis Bridge, near the Sportpaleis in Antwerp

Groundworks & placement concrete change Ghent-Sint-Pieters

Taveirne carried out groundworks at Ghent-Sint-Pieters station during the night in early November. A concrete switch of about 70m was also installed.

Renewal of Zeebrugge tram tracks

Taveirne is currently working on the first phase of the complete renewal of the tram tracks in Zeebrugge.  

New tunnel under railway line – Herentals

In cooperation with De Vlaamse Waterweg nv and Infrabel, a new tunnel was pushed under the railway line at De Beukelaer-Pareinlaan in Herentals during the weekend of 9 and 10 July.

Track and level crossing renewal – Melle

Commissioned by Infrabel, Taveirne renewed the tracks and level crossings along the route of Melle.

Avenue General Jacques in Brussels

Installation of new tram tracks in General Jacques Avenue, between the corners of Sterreplein and Boondaalsesteenweg, incl. the beginning of Buyllaan and Renbaanlaan.

Infrabel Framework Agreement Area NW Ghent

Complementary works at renewing sleepers with track renewal train P93 and sifting ballast with
ballast-sifting-train C75 at several locations in the area NW Ghent.
Renewing railroad crossings.
Renewing (ballast, sleepers and rails) main tracks.

New tram depot in Ostend

Construction of the new tram depot involves 8 tracks where a total of more than 60 trams can be stationed.
In commission of Cordeel

Placement of new tramway line 9 (High-Jette)

The project Line 9, is an ambitious project realized in corporation with the STIB, Brussels Capital Region, Beliris and Jette.

Extension of the tram line 4 to campus UZ Ghent

Railway line over 850 m double track with six switches, two crossings, 5 rail assembly systems and the control of the switches.

New Railway Line along the Albertkanaal at Oevel

Removing the old tracks and constructing a new railway line.
Under contract to De Scheepvaart

HIGH SPEED LINE Brussels – Cologne

Installation of tracks and catenaries for the high-speed line section between Liège and the German border.

Renewal of the Tramway tracks between Lille Flandres en Croisé Laroche

Renovation of a single track section between the terminus of Lille Flanders station and Croisé Laroche, 4 km containing 9 stations.

Light Rail Metro in Charleroi – Gosselies Branch

The whole project entails laying around 13.5 km of single track on concrete, and around 1.5 km of ballast single track.
Under contract to Tec

Laying of tram tracks in the Avenue Louise, Brussels

Laying of 3,610 m of single tram tracks situated at Anvenue Louise, from Place Stéphane to Rue Lauters.
Under contract to MIVB/STIB

Track renovation of the Blankenberge thoroughfare

Renewal of the double track including road crossings, and points and crossings, improvement of the track foundation, adaptation of the signalling …
Under contract to De Lijn

HSL Brussels-Amsterdam – zone between Antwerp-Berchem and Noorderdokken

Construction of the tracks and points and crossings, including both drilled shafts.
Under contract to TUC RAIL

Ostend Master Plan

The removal, installation and renewal of points and crossings, tracks on the main and secondary track
Under contract to Infrabel

New tram tracks in Ittre

Renewal and creation of 1,700 m of single tram track and of a track connection at Avenue de la Chasse and Place Saint-Pierre in Ittre.
Under contract to STIB/MIVB

Reconstruction of tracks on the N1 at Bredabaan in Merksem

Renewal of tracks, execution of road surface works and also cable works
Under contract to AWV