Commissioned by Infrabel, Taveirne carried out extensive railway works at the Bethune junction in Kortrijk during a total line closure of just 8 days.
Track renewal works at Bethune junction – Kortrijk
Commissioned by Infrabel, Taveirne carried out extensive railway works at the Bethune junction in Kortrijk during a total line closure of just 8 days.
In Halle, our teams are working across four intensive TLO weekends to renew no fewer than eight railway switches. During these weekends, work continues around the clock, 24/7, to minimize the impact on rail traffic as much as possible.
During the weekend of 15–16 November, following pre-assembly, two P215 switches were replaced in Schaerbeek, using our PEMs and LEMs, and two tracks of approximately 75 metres were renewed.
During the weekend of 8 and 9 November Taveirne installed three P1150 turnouts at the Aalter-Bellem worksite on the Ghent–Ostend line.
During the weekends of 13–14 and 20–21 June, Taveirne installed four new railway switches as part of phase 1.1 of the Dendermonde Master Plan.
Two additional tracks are being laid on Belgium’s busiest railway line (L50), between Ghent and Bruges.SNCB is already integrating the new tracks into the June timetable, which will lead to smoother and more punctual train connections.